Facility

The New Home for Lancer Recreation: The Inside Scoop on the $73 million Project

by: Justin Peters  Despite the delays, deferrals, postponements and cancellations the University community has faced as a result of the pandemic, construction on the Lancer Sport and Recreation Centre (LSRC) is well underway and could provide some much-needed optimism for students, staff and faculty. The inauguration of the $73 million athletic centre is set for spring 2022. The development of the LSRC experienced a 27-day delay at the start of the COVID-19 pandemic in March, but has since made up for the lost time and is expected to open its doors to the public in May of 2022, on schedule.

By |Wed, Mar 3rd, 2021, 1:46PM|News, Sports|
Go to Top